Monday

April 13

Tuesday

April 14

Wednesday

April 15

Thursday

April 16

Friday

April 17

9:00 � 10:00

Welcome and Introductions, including Safety Lecture

8:30 � 9:30

Project Planning and Management within a Lifecycle Mgmt Framework (P. Booth)

8:30 � 9:30

Introduction to Decommissioning� (L. Boing)

8:30 � 9:30

Safety Assessment (D. Draper)

8:30 � 9:30

RESRAD (Onsite) Overview

(C. Yu)

10:00 � 10:30

Course Overview & Objectives

(K. Smith and L. Boing)

9:30 � 10:15

Determining End States and Future Site Uses (K. Smith)

9:30 � 10:30

Environment, Safety & Health Issues (T. Hansen)

9:30 � 10:30

Building Characterization (T. Hansen)

9:30 � 10:30

RESRAD (Onsite) Demonstration

(D. LePoire)

 

 

 

 

 

10:45 � 11:30

IAEA Networks & Resources IDN | ENVIRONET

(P. Booth and L. Boing)

10:30 � 11:30

Stakeholder Engagement

(P. Booth)

10:45 � 12:00

Waste Management (L. Boing)

10:45 � 11:45

Decontamination Technologies (R. Demmer)

10:45 � 12:00

RESRAD (Onsite) hands-on exercise

(C. Yu and D. LePoire)

 

11:30 � 12:00

Argonne Case Study | D&D

(L. Boing and L. Moos)

11:30 � 12:15

Conceptual Site Models

(P. Booth)

 

 

 

 

 

1:00 � 3:00

Participants� Introductory Presentations

1:15 � 3:15

Painful Site Conceptual Site Model, hands-on exercise

1:00 � 1:45

Material Clearance (D. Draper)

 

12:45 � 1:45

Dismantling Technologies (L. Boing)

1:00 � 2:00

RESRAD-BUILD Overview

(C.Yu)

 

1:45 � 3:00

Cost Estimation and Contracting for D&D Projects (J. Carignan)

1:45 � 2:15

Remote Systems

(Y. Park)

2:00 � 3:00

RESRAD-BUILD Demonstration

(D. LePoire)

3:00 � 3:30

Records (D. Draper)

2:15 � 3:00

Final Status Surveys (T. Hansen)

 

 

 

 

 

3:15 � 5:00

Participants� Introductory Presentations, cont.

 

3:30 � 4:30

Conceptual Site Model Group Presentations to Stakeholders

(P. Booth)

3:45 � 5:00

D&D Planning hands-on exercises

(L. Boing)

 

3:15 � 5:00

D&D Cost Estimation/Work Breakdown Structure hands-on exercises

(L. Boing)

3:15 � 5:00

RESRAD-BUILD hands-on exercise

(C. Yu and D. LePoire)

 

4:30 � 5:00

Overview of Dose and Risk Assessment

(C. Yu)

 

 

7:00 Seminar at Hotel:

Case Study of Zion Nuclear Power Plant Decommissioning (N. Williams, Energy Solutions)

 

 


 

Monday

April 20

Tuesday

April 21

Wednesday

April 22

Thursday

April 23

Friday

April 24

8:30 � 9:30

Waste Disposal � Part 1

(V Rogers Jr)

8:30 � 10:15

Introduction to Env. Site Characterization;|

Env. Data Collection Realities

(B. Johnson)

8:30 � 10:30

Surface Soils: Gamma Walkover Surveys;|

Gamma Walkover Case Study|

Incremental Soil Sampling Case Study (B. Johnson)

8:30 � 9:15

Remedial Action Alternatives

(L. Martino)

8:30 � 10:30

Participants Action Plan Presentations

9:30 � 10:30

Evolving Technologies

(J. Nokhamzon)

9:15 � 10:00

ER Cost Estimation

(L. Martino)

 

 

 

 

 

10:45 � 11:30

Waste Disposal � Part 2

(V. Rogers)

10:30 � 12:30

Measuring Radionuclides in the Environment;|

Subsurface Characterization:|

Incremental Sampling Strategies for Surface Soils

(B. Johnson)

10:45 � 11:30

Exercise in Developing a Characterization Program

(B. Johnson)

10:15 � 11:00

ER Cost Estimation Exercise

(L. Martino)

10:45 � 12:45

Participants Action Plan Presentations

11:30 � 12:30

Case Study: University of Buffalo Research Reactor D&D

(D. Miller)

11:00 � 11:45

Site Closure: Final Status Surveys and MARSSIM

(B. Johnson)

 

 

 

 

 

2:00 � 5:00

D&D Exercise and Visit to EPA Warehouse | Mobile_Unit_for_In-Situ_Characterization.pdf

(L. Boing and USEPA Region V)

2:00 � 5:00

Site Characterization Equipment Demonstrations and Exercise

(B. Johnson and USEPA

Region V)

12:30 � 1:15

Evolving Conceptual Site Models: Case Studies

(Bob Johnson)

12:45 � 1:30

Case study: French D&D Project

(J. Nokhamzon)

1:45 � 2:15

Key Concepts

(L. Boing and P. Booth)

 

1:15 � 3:15

Updating the Conceptual Site Model, hands-on exercise (small groups)

(B. Johnson and P. Booth)

1:30: 2:15

Case study: Plum Brook Research Reactor D&ER Project

(A. Lombardo)

2:15 � 3:00

Closing Remarks

2:15 � 3:00

Case study: Permeable Treatment Wall at West Valley Site (L. Durham)

 

 

 

3:30 � 5:00

Conceptual Site Model Group Presentations to Stakeholders

(B. Johnson and P. Booth)

3:15 � 4:00

Case study: Approach to Remediation Following the Fukushima Accident (P. Booth)

4:00 � 5:00

Participants Prepare Action Plans

 

 

7:00 Seminar at Hotel:

IAEA CIDER Project Overview (H. Monken Fernandes) and French Waste Clearance Process (J. Nokhamzon)

 

 

 

extra